Site Update - Issue #11 - June, 2008
 
 

Site Update June 30, 2008 

General 

Storm drainage installation complete;
Final grade of the landscaping continues with the spreading of top soil and planting of grass; 
 
Infrastructure 

  • High voltage and Low voltage wiring has commenced allowing the C-type and B-type apartments to be connected to the site power grid.
  • Final installation of components for the sewage farm has commenced;
  • The installation of the generator to be undertaken with the installation of the High voltage circuit has commenced;
  • Construction of the roads behind C-type apartments and access to Club House and the spur to the B-type apartments has commenced;  
 

C-Type Apartments 

Block 11 

  • Final interior painting and installation of door and window hardware complete;
  • Installation of WC’s, baths, showers, doors, vanities, hot water heaters and kitchens commenced;
 

Block 6 

  • Final installation of WC’s, baths, showers, doors, vanities, hot water heaters and kitchens;
 

Block 1 

  • Final installation of WC’s, baths, showers, doors, vanities, hot water heaters and kitchens in apartments 102 and 103; 
 

B-Type Apartments 

Block 2 and 3 

  • Tiling in level 1 and level 2 bathrooms 90% completed
  • Level 1 doors installed
  • All outlets, switches and fan controls installed
 

Block 7, 8, 15 and 16 

  • Level 2 tiling complete
  • Level 1 tiling well advanced
  • All switches, outlets, fan controls installed
  • Door installation level 1 commenced
 

A-Type Apartments 

Block 4 

  • Level 1 and 2 floors installed 90%
  • Level 3 plastering at 60%
  • Internal wiring level 1 and level 2 complete
 

Block 5 

  • Flooring in level 2 complete
  • Electrical wiring level 1, 2 and 3 compete
 

Block 9 

  • Flooring installed on level 1 and level 2
  • Electrical wiring installed in level 1, 2 and 3
 

Block 10 

  • Flooring in level 1 and 2 complete
  • Internal wiring level 1, 2 and 3 complete
 

Block 17 

  • Internal wiring level 2 complete
  • Plastering level 3 commenced
  • Air conditioning installation in all units continues
  • Infrastructure installation for all A-Types commence
 

Townhouses 

TH 25 

  • Interior and exterior doors installed
  • Tiling completed at 80%
  • Interior and exterior priming complete
 

TH 24 

  • Interior and exterior doors installed
  • Tiling and priming complete
 

TH 23 

  • Interior and exterior doors commenced installation
  • Tiling at 20%
  • Priming complete
 

TH 22 

  • Door installation, tiling and priming commenced
 

TH 21 and 20 

  • Tiling and priming commenced
 

TH 19, 18 and 17 

  • Plastering complete
  • Interior painting and priming commenced
 

TH 16, and 15 

  • Plastering underway
 

TH 14 

  • Plastering underway
  • Roof completed at 90%
 

TH 12, 11 and 10 

  • Plastering completed at 90%
  • Block 10 primed
  • Interior priming on Block 11 commenced